Technical Services carried out the replacement of a 752 MVA transformer, which involved dismantling the faulty unit and transporting a new transformer to destination.
The transportation process presented significant challenges due to the complexity of the route and logistical constraints.
Our dedicated team worked 24/7 to ensure the installation of the new transformer. The project scope included all associated work such as cable testing, supply and installation of a new Gas Insulated Busbar (GIB), and commissioning of protection system, and final safe energization.
This achievement reflects our ongoing commitment to reliability, technical excellence, and timely power infrastructure upgrades.
Grid • National Grid
752 MVA Transformer Replacement Project
Client
National Grid
Location
Saudi Arabia
Grid Projects
01